Thieme Drive Riverbank Repair 2010 - 2011
Saint Marys River, Fort Wayne, Indiana
Placing Gabion Layers 2 and 3
All Photos Copyright © 2010 - 2011 by Robert E Pence
Return to Riverbank Repair Index
October 7, 2010 - Moving up with second and third layers of gabions
I knew that the land near the river had been filled extensively some time in the late nineteenth or early twentieth century, but looking at the excavated
area, it appears that there are two layers of fill, interspersed with building rubble and household items like bottles and broken dishes. I waited until
after hours to climb down into the work area for a closer look.
At least three old drains of vitreous tile once ran into the river. The city ran a camera up into them to see if they still were connected to anything.
They aren't.
October 8, 2010
October 12, 2010
October 13, 2010
October 15, 2010
Return to Riverbank Repair Index